Fuller Road CR-53 Over Tributary of Steuben Creek
RegrexSolutions provided complete estimating services for this critical bridge replacement project where Fuller Road (CR-53) crosses a tributary of Steuben Creek. The scope included demolition of the aging structure and construction of a new 65-foot single-span concrete bridge with reinforced abutments, designed to meet NYSDOT hydraulic requirements for 100-year flood events. The project area encompassed 1.2 acres of sensitive riparian zone, requiring specialized environmental mitigation measures.
Services Delivered
-
Structural Takeoffs:
-
420 CY of Class AA concrete for deck/abutments
-
38 tons of rebar (#6-#11) with epoxy coating
-
1,850 SF of permanent steel sheet piling
-
-
Civil/Sitework Estimates:
-
Temporary cofferdam installation
-
Stream channel realignment (285 LF)
-
Riprap bank stabilization (320 CY)
-
-
Specialty Systems:
-
Bridge railing (Type NYSDOT 5-01)
-
Underdeck drainage systems
-
Approach guardrail transitions
-
Technical Challenges Addressed
✔ Environmental Compliance: Minimized in-water work windows to protect trout habitat ✔ Geotechnical: Designed for poor bearing capacity soils (N-values <10) ✔ Traffic Maintenance: Phased construction with temporary signalization
Project Impact
-
Cost Savings: 22% reduction through value-engineered falsework design
-
Accuracy: 97.5% material match on as-built quantities
-
Schedule: Met NYSDOT’s 120-day construction window requirement